{"entity":{"name":"Acme Supplies SRL","registration":"BE0123456789","site":"Production workshop — Zone Industrielle Est, 1040 Brussels"},"plan_period":{"start_date":"2026-04-01","end_date":"2026-06-30"},"products":[{"sku":"ACM-SHELF-STD","description":"Standard shelving bracket, powder-coated steel, 200×150 mm","planned_quantity":12000,"unit":"pcs","target_completion_date":"2026-06-15","production_line_or_cell":"Line A — stamping + powder coating","raw_material_requirements":[{"material":"Cold-rolled steel sheet 1,5 mm (DX51D+Z)","required_quantity":3600,"unit":"kg","available_quantity":4200},{"material":"Powder coat RAL 9005 matte black","required_quantity":180,"unit":"kg","available_quantity":240},{"material":"Cardboard boxes 300×200×80 (qty 50 brackets)","required_quantity":240,"unit":"pcs","available_quantity":300}],"labour_hours_planned":720,"capacity_constraint":"Powder coat oven throughput — 1.500 brackets / shift"},{"sku":"ACM-SHELF-HD","description":"Heavy-duty shelving bracket, powder-coated steel, 300×200 mm, reinforced","planned_quantity":4500,"unit":"pcs","target_completion_date":"2026-06-22","production_line_or_cell":"Line A — stamping + powder coating","raw_material_requirements":[{"material":"Cold-rolled steel sheet 2,0 mm (DX51D+Z)","required_quantity":2250,"unit":"kg","available_quantity":1800},{"material":"Powder coat RAL 7016 anthracite","required_quantity":90,"unit":"kg","available_quantity":120},{"material":"Cardboard boxes 400×250×100 (qty 20 brackets)","required_quantity":225,"unit":"pcs","available_quantity":260}],"labour_hours_planned":450,"capacity_constraint":"Same oven as ACM-SHELF-STD — share the 1.500/shift envelope"},{"sku":"ACM-CABLE-CLIP-M","description":"Cable clip assembly, nylon + steel wire, 25 mm","planned_quantity":80000,"unit":"pcs","target_completion_date":"2026-06-28","production_line_or_cell":"Line B — assembly cell 2","raw_material_requirements":[{"material":"Nylon housing NH-25 (injected)","required_quantity":80000,"unit":"pcs","available_quantity":62000},{"material":"Steel wire 1,2 mm, galvanised","required_quantity":640,"unit":"kg","available_quantity":900},{"material":"Bulk bag 500 pcs","required_quantity":160,"unit":"pcs","available_quantity":200}],"labour_hours_planned":520}],"schedule_overview":"Q2 2026 MPS covers 3 high-runner SKUs across two production lines. Line A (stamping + powder coat) is the critical path: standard and heavy-duty brackets share the powder-coat oven, which is scheduled at 92% utilisation. ACM-SHELF-HD runs first (week 14–17) to lock the customer PO commitment LEM-2026-0312 and ENT-2026-0088; standard brackets run week 17–23. Line B runs cable clip assembly in parallel throughout the quarter on a pull signal from finished-goods stock reorder points. Maintenance windows: Line A preventive 2026-04-12 and 2026-05-24; Line B preventive 2026-04-19.","capacity_utilisation_pct":92.0,"risks":["Nylon housing NH-25 shortage — 18.000 pcs gap vs. plan; open PO ACM-PO-2026-0207 with Polymar GmbH, confirmed delivery 2026-04-23. Monitor weekly.","2,0 mm steel sheet for HD brackets is 450 kg short; procurement negotiating framework spot-buy with secondary supplier to de-risk week 15 start.","Powder coat oven is the plant bottleneck at 92% utilisation — any unplanned downtime on Line A directly risks the HD bracket target date."],"planner":{"name":"Nathalie Claes","title":"Production Planner"}}