{"entity":"Acme Supplies SRL","project_name":"Warehouse Management System Rollout","project_code":"WMS-2026","project_manager":"Sophie Dubois","baseline_date":"2026-04-01","version":"1.2","planned_start":"2026-04-01","planned_end":"2026-12-15","phases":[{"id":"P1","name":"Initiation and planning","start":"2026-04-01","end":"2026-05-15","lead":"Sophie Dubois","percent_complete":100},{"id":"P2","name":"Design and procurement","start":"2026-05-01","end":"2026-06-15","lead":"Sophie Dubois","percent_complete":85},{"id":"P3","name":"Build and configure","start":"2026-06-01","end":"2026-08-15","lead":"Paolo Bianchi","percent_complete":40},{"id":"P4","name":"Test and train","start":"2026-08-15","end":"2026-10-15","lead":"Mark De Vos","percent_complete":0},{"id":"P5","name":"Deploy and hypercare","start":"2026-10-15","end":"2026-12-15","lead":"Sophie Dubois","percent_complete":0}],"tasks":[{"id":"T1.1","name":"Project kick-off meeting and team mobilisation","owner":"Sophie Dubois","start":"2026-04-01","end":"2026-04-05","duration_days":5,"dependencies":[],"status":"done","percent_complete":100},{"id":"T1.2","name":"Charter and governance sign-off","owner":"Thibault Moreau","start":"2026-04-06","end":"2026-04-10","duration_days":5,"dependencies":["T1.1"],"status":"done","percent_complete":100},{"id":"T1.3","name":"Requirements elicitation (inbound)","owner":"Anouk Jansen","start":"2026-04-11","end":"2026-04-30","duration_days":14,"dependencies":["T1.2"],"status":"done","percent_complete":100},{"id":"T1.4","name":"Requirements elicitation (outbound)","owner":"Anouk Jansen","start":"2026-04-15","end":"2026-05-08","duration_days":16,"dependencies":["T1.2"],"status":"done","percent_complete":100},{"id":"T1.5","name":"Requirements baseline sign-off","owner":"Karim El Houari","start":"2026-05-11","end":"2026-05-15","duration_days":5,"dependencies":["T1.3","T1.4"],"status":"done","percent_complete":100},{"id":"T2.1","name":"Vendor RFP and shortlist","owner":"Julie Leroy","start":"2026-05-01","end":"2026-05-20","duration_days":14,"dependencies":["T1.2"],"status":"done","percent_complete":100},{"id":"T2.2","name":"Vendor demos and reference checks","owner":"Julie Leroy","start":"2026-05-15","end":"2026-05-25","duration_days":7,"dependencies":["T2.1"],"status":"done","percent_complete":100},{"id":"T2.3","name":"Vendor selection and contract negotiation","owner":"Marie Laurent","start":"2026-05-25","end":"2026-06-05","duration_days":9,"dependencies":["T2.2"],"status":"in_progress","percent_complete":70},{"id":"T2.4","name":"SOW and contract signature","owner":"Thibault Moreau","start":"2026-06-05","end":"2026-06-10","duration_days":3,"dependencies":["T2.3"],"status":"not_started","percent_complete":0},{"id":"T3.1","name":"Infrastructure provisioning (prod, test)","owner":"Paolo Bianchi","start":"2026-06-10","end":"2026-06-24","duration_days":10,"dependencies":["T2.4"],"status":"not_started","percent_complete":0},{"id":"T3.2","name":"WMS base configuration","owner":"Vendor consultant","start":"2026-06-25","end":"2026-07-20","duration_days":18,"dependencies":["T3.1"],"status":"not_started","percent_complete":0},{"id":"T3.3","name":"Sage ERP integration build","owner":"Paolo Bianchi","start":"2026-07-01","end":"2026-07-25","duration_days":19,"dependencies":["T3.1"],"status":"in_progress","percent_complete":25},{"id":"T3.4","name":"Carrier API integration build","owner":"Paolo Bianchi","start":"2026-07-10","end":"2026-08-05","duration_days":19,"dependencies":["T3.1"],"status":"not_started","percent_complete":0},{"id":"T3.5","name":"Master data migration","owner":"Anouk Jansen","start":"2026-07-20","end":"2026-08-10","duration_days":16,"dependencies":["T3.2"],"status":"not_started","percent_complete":0},{"id":"T3.6","name":"Barcode hardware rollout","owner":"Mark De Vos","start":"2026-07-15","end":"2026-08-15","duration_days":22,"dependencies":[],"status":"not_started","percent_complete":0},{"id":"T4.1","name":"System test (integrated)","owner":"Paolo Bianchi","start":"2026-08-15","end":"2026-09-05","duration_days":15,"dependencies":["T3.2","T3.3","T3.4","T3.5"],"status":"not_started","percent_complete":0},{"id":"T4.2","name":"User acceptance testing (UAT)","owner":"Mark De Vos","start":"2026-09-05","end":"2026-10-05","duration_days":22,"dependencies":["T4.1"],"status":"not_started","percent_complete":0},{"id":"T4.3","name":"Operator training","owner":"Lisa Nguyen","start":"2026-09-15","end":"2026-10-15","duration_days":22,"dependencies":["T3.6"],"status":"not_started","percent_complete":0},{"id":"T4.4","name":"UAT sign-off and go-live readiness review","owner":"Karim El Houari","start":"2026-10-12","end":"2026-10-15","duration_days":3,"dependencies":["T4.2","T4.3"],"status":"not_started","percent_complete":0},{"id":"T5.1","name":"Cut-over dress rehearsal","owner":"Sophie Dubois","start":"2026-11-01","end":"2026-11-05","duration_days":5,"dependencies":["T4.4"],"status":"not_started","percent_complete":0},{"id":"T5.2","name":"Go/no-go checkpoint","owner":"Thibault Moreau","start":"2026-11-10","end":"2026-11-10","duration_days":1,"dependencies":["T5.1"],"status":"not_started","percent_complete":0},{"id":"T5.3","name":"Production cut-over","owner":"Sophie Dubois","start":"2026-11-14","end":"2026-11-15","duration_days":2,"dependencies":["T5.2"],"status":"not_started","percent_complete":0},{"id":"T5.4","name":"Hypercare (90 days)","owner":"Paolo Bianchi","start":"2026-11-16","end":"2026-12-15","duration_days":22,"dependencies":["T5.3"],"status":"not_started","percent_complete":0},{"id":"T5.5","name":"Project close and hand-over to run-state","owner":"Sophie Dubois","start":"2026-12-10","end":"2026-12-15","duration_days":5,"dependencies":["T5.4"],"status":"not_started","percent_complete":0}],"critical_path":"T2.4 -> T3.1 -> T3.2 -> T3.5 -> T4.1 -> T4.2 -> T4.4 -> T5.1 -> T5.3. Total float on this path is 0 days; any slippage immediately pushes go-live.","assumptions":["Resource availability as committed in the charter (vendor and internal).","No new scope introduced outside CCB approval.","Sage ERP APIs stable during the integration build window.","Working days calendar excludes Belgian public holidays and the retail peak freeze (27 November to 31 December)."],"plan_owner":{"name":"Sophie Dubois","title":"Programme Manager"}}